Manufacturing Space Power Requirements in the GTA
November 19, 2026

Manufacturing Space Power Requirements in the GTA

By Michael Law · Industrial Real Estate Broker, Lennard Commercial Realty

Electrical switchgear serving a manufacturing plant

A manufacturing space needs enough electrical service for every machine you will run at the same time, today and after planned growth, at the voltage and phase your equipment expects. In Ontario that usually means adding up your loads, leaving a margin under the 80% limit in the electrical code, and getting the local utility to confirm in writing what it can deliver. Do this before you sign a lease, because upgrading a service can take longer than the fit-out itself.

This guide explains how to size your power need, which service characteristics matter, how to verify a building’s real capacity, and what lead times to plan for in Toronto and the wider GTA.

Michael Law | Lennard Commercial
mlawrealestate.com
Check Power Before You Lease
Michael Law advises industrial tenants on site selection and lease negotiations across the GTA, helping them assess whether a space fits their needs.
Explore industrial real estate

TL;DR

  • Build a load schedule first: list every process and non-process load, then work out peak and design demand, not just the sum of nameplates.
  • Ontario’s electrical code limits load demand to 80% of the service rating, so a 400 A service is practically a 320 A service.
  • Match voltage and phase to your equipment. Ontario industrial buildings commonly run 347/600V or 120/208V distribution.
  • Get the utility’s answer in writing. Toronto Hydro says quotations typically take up to 60 days, and projects can take months or years.
  • Make the lease conditional on confirmed capacity, not on a listing that says “expandable power”.

Table of Contents

Why power decides whether a manufacturing site works

A warehouse can often operate on modest service. A plant with CNC machines, compressors, ovens, chillers or high-power welding cannot. If the building does not have the capacity, you either pay for an upgrade, wait for the utility, or pick another building.

In the GTA this matters more than it used to. Vacancy has been tight, good buildings go quickly, and tenants often commit to a space before anyone has checked the electrical room. That is how a company ends up with a signed lease and a machine it cannot switch on. Our Toronto industrial vacancy rate page tracks how little room tenants have to shop around, which is exactly why power should be on your site-selection checklist from day one, not in the final week of due diligence.

The four terms that cause most confusion

Listings and utility documents use several terms that sound alike. They are not interchangeable.

Connected load

Connected load is the total rating of all electrical equipment installed, as if everything ran at once. It is the sum of nameplates: motors, heaters, lighting, HVAC, office loads. It is a ceiling, not a forecast.

Peak demand

Peak demand is the highest load the facility actually draws over a period, usually measured over a short interval. Equipment rarely runs all at the same time or at full rating, so peak demand is normally lower than connected load. It is the number that tells you how much capacity you really use.

Service capacity

Service capacity is what the building’s incoming electrical service is rated to carry, expressed in amps at a given voltage. It is set by the size of the service conductors, the main switch, the switchgear and the transformer that feeds them.

Available capacity

Available capacity is the headroom left after existing loads, and it has two layers. There is what is spare inside the building’s own equipment, and there is what the utility’s local network can supply to that address. A building can have a large main switch and still sit on a feeder with no room to spare. This is the distinction that listings blur.

Step 1: Build a load schedule

The standard way to estimate need is an industrial load schedule. Open Electrical describes the method: list process and non-process loads, collect each one’s rating, power factor and efficiency, classify them by switchboard, duty and criticality, then calculate consumed, operating, peak and design loads.

In practice, work through these steps:

  1. List every load. Production machines, compressors, conveyors, dust collection, ovens, refrigeration, HVAC, lighting, battery chargers, office equipment and yard equipment.
  2. Record ratings. Get kW or horsepower, voltage, phase and full-load amps from the nameplate or the manufacturer’s data sheet.
  3. Apply efficiency and power factor. Active power is measured in kW. Reactive loading is measured in kVAr. Low power factor and motor efficiency change the consumed load, so a motor’s output rating understates what the service must carry.
  4. Assign duty. A press that cycles for 20 seconds in every minute does not draw its rating continuously. A chiller does. Be honest about which is which.
  5. Group by panel. This shows where distribution equipment must be sized, not only the main service.
  6. Add future loads. Save on Energy’s guidance says an assessment should compare the total demand of all equipment with installed service capacity, and that future loads such as EV charging and heat pumps belong in the calculation. For a manufacturer, add the second shift, the second line and the machine you plan to buy in three years.

The output is a design load you can hand to a landlord, an electrician and the utility. Without it, every conversation about “enough power” is guesswork.

A worked example

Suppose a metal fabricator lists 250 kW of connected production equipment, 60 kW of HVAC and lighting, and plans to add a 90 kW line in year three. Total connected load is 400 kW. After duty factors, the owner estimates peak demand at roughly 70% of that, or 280 kW. With the planned line fully added, the design load rises toward 370 kW.

At 600V three-phase, kVA divided by (1.732 × 0.6) gives amps. At a power factor of 0.9, 370 kW is about 411 kVA, which is roughly 395 A. Our arithmetic is simple, and the result shows why “a 400 A service” is not enough: after the code’s 80% limit, you would need a service rated higher than 490 A. The next standard size up is likely, and that may cross a utility threshold, as covered below.

These figures are illustrative. Your electrical engineer should run the real calculation.

Step 2: Match voltage, phase and distribution

Capacity is only part of it. The service has to deliver the right kind of power.

Save on Energy notes that Ontario commercial, institutional and industrial buildings commonly use 120/208V and 347/600V distribution, that capacity is expressed in amps, and that equipment operates at different voltages. For a tenant, that raises practical questions:

  • What voltage do your machines require? Many industrial machines are built for 600V three-phase in Canada. Imported equipment may be rated for 480V or 380V and need a step-down transformer. Check the nameplate before you assume.
  • Is the building three-phase? Older flex and showroom units are sometimes served at 120/208V, which is fine for light assembly and offices but limiting for heavy motors.
  • Where does the transformer sit? Landlord-owned transformers, pad-mounted units and interior transformer rooms affect who pays for changes.
  • Is there room in the electrical room? Adding panels or switchgear needs wall space, clearances and ventilation.

Equipment that needs a specific voltage the building does not provide will require a transformer, which costs money, takes floor space and adds losses. Include it in your occupancy cost, not as an afterthought.

When the service becomes a primary service

Larger loads cross a line where the customer takes supply at high voltage and owns more of the equipment. Utilities set their own thresholds. As one example, Enova Power’s primary-service guideline says a site will generally require primary service when service size exceeds 400 A at 347/600 V or 600 A at 120/208 V, unless the utility permits otherwise. The same document lists typical primary-service infrastructure: high-voltage duct banks, pad-mounted transformers or transformer rooms, switchgear, low-voltage duct banks and a building electrical room.

Pad-mounted transformer beside a manufacturing facility

Enova serves its own territory, so confirm the threshold with whichever utility serves your target address. The principle holds across Ontario: once your load passes a certain size, you are no longer a simple connection. You are building electrical infrastructure, and that changes the cost, the timeline and the lease conversation.

Step 3: Respect the 80% rule

The most useful single number for a tenant comparing buildings is the code limit. Save on Energy states that the Ontario Electrical Safety Code prescribes that load demand must not exceed 80% of the service rating, and that a larger service is required if new equipment would push past that level.

That has direct consequences:

Service rating Maximum load demand at 80%
200 A 160 A
400 A 320 A
600 A 480 A
800 A 640 A

When a listing says “600 A, 600V”, the usable figure for new equipment is lower once existing tenants’ loads and the 80% limit are counted. Ask the landlord for the building’s existing demand, not only the nameplate rating of the main switch.

Step 4: Verify capacity before you commit

A listing’s electrical line is a starting point. Treat phrases such as “expandable power” or “heavy power” as unverified until someone has confirmed them.

What to ask the landlord

  • The service size, voltage, phase and who owns the transformer.
  • Recent single-line diagrams and electrical drawings.
  • Existing demand history, if available, and any other tenants on the same service.
  • Whether the landlord will permit service upgrades, where equipment can go, and who pays.
  • Any prior utility correspondence about upgrades at the address.

What to ask the utility

The utility is the party that can say what the network can supply. The process differs by utility, but the pattern is consistent.

Toronto Hydro’s guide asks for project information including a site plan, proposed electrical drawing, building permits, zoning certifications and load calculations. It then reviews the details and issues a job quote or offer to connect that sets out project details, timelines and financial requirements. The load schedule you built earlier is what feeds this step.

Outside Toronto Hydro’s territory, a large share of GTA fringe areas are served by Hydro One, which requires project details and supporting documents such as a single-line diagram and primary-fusing information. It reviews the application, may meet on site and identifies line expansions or upgrades. Its distribution load capacity map offers high-level information on available capacity for prospective connections. Hydro One says the map is informational only and does not replace direct coordination, so use it to screen sites, not to approve them.

Mississauga, Brampton, Vaughan, Markham and other municipalities have their own local distribution companies, each with its own application forms and standards. Find out which one serves the address early.

What to ask the utility — overview diagram

Bring in a licensed electrician

Save on Energy’s fact sheet recommends that a licensed electrician assess the service capacity available and determine any extra capacity needed for new loads. For manufacturing, an electrical engineer who can produce a stamped load calculation is worth the fee. You are paying a small amount to avoid a very large mistake.

Step 5: Know the code, inspection and licensing steps

In Ontario, electrical work is not finished when the wires are connected. ESA’s 2026 fee guide states that the Electrical Safety Authority is the sole organization authorized under provincial legislation to perform electrical inspection services, and that the Ontario Electrical Safety Code requires inspection of electrical installations. It also notes that Part VIII of the Electricity Act generally requires electrical contracting businesses to hold an ECRA/ESA licence, subject to exemptions.

For you, that means three things:

  • Use a licensed electrical contractor for any new service, panel or equipment connection.
  • Build ESA inspection into the schedule. Toronto Hydro’s guide says the customer or contractor must complete applicable civil and electrical work, arrange an ESA safety inspection and satisfy the utility’s final inspection before connection.
  • Do not plan to “switch on early”. Energization follows authorization and inspection.

Step 6: Plan for utility lead times

This is the section that surprises most tenants. Electrical upgrades are slow, and the slowest part is usually not construction.

On its service upgrade page, Toronto Hydro says a representative normally contacts the applicant within 10 business days and that the quotation or offer process typically takes up to 60 days after all required information arrives. Long-lead materials may call for an Advanced Material Procurement Deposit on top of a design pre-payment. Once ESA authorization and the service conditions are complete, upgrades are scheduled in approximately five business days for services of 750 V or less, and ten business days for services above 750 V.

The wider range is longer. Toronto Hydro’s service connection guidance says projects can take weeks to several months or years depending on complexity. It recommends submitting three months to three years ahead for low-voltage projects under 600 V, and at least six months, up to five years, for high-voltage projects of 600 V or more.

For a tenant on a 5 to 10 year lease, those numbers decide the whole deal. If your production start date is fixed, a building that needs a utility upgrade is a risk to be priced, not a bargain to be taken.

How to protect yourself in the lease

  • Make the lease conditional on written utility confirmation of the capacity you need.
  • Negotiate free rent or a delayed commencement date until power is energized.
  • Specify who pays for the upgrade, who owns the new equipment, and whether it must be removed at lease end.
  • Get landlord consent for electrical work and equipment placement upfront.
  • Confirm there are no restrictions on additional transformers, generators or outdoor pads.

Our guide to due diligence when leasing industrial space and the broader commercial due diligence guide show where these conditions sit in the process.

Step 7: Account for expansion, redundancy and backup

Sizing for today’s equipment and nothing more is the most common regret we hear about.

Expansion. Ask the utility and the engineer what the building can reach, not just what it has. Space for a second transformer, spare conduit and room in the electrical room are cheap to secure at lease signing and expensive later.

Redundancy. If an outage would ruin a batch, damage product or stop a customer shipment, you need to know how the site is fed. Enova’s guideline says it may require multiple transformers, high-voltage duct banks or switchgear for a looped service configuration, which can minimize outages and aid scheduled maintenance. Ask whether your target building has a single feed or a looped one.

Backup power. Generators and transfer switches need outdoor pad space, fuel storage rules and landlord approval. Check that the lease and zoning permit them before you design around one.

Efficiency. Lower consumption reduces both the size of the service you need and your monthly bill. High-efficiency motors, variable-speed drives and power factor correction all help. Our article on industrial property upgrades for value and efficiency covers improvements that tenants and owners commonly weigh.

Which types of manufacturing need the most scrutiny

Not every operation faces the same problem. As a rough guide:

  • Light assembly and packaging. Usually modest demand. Check voltage and the number of outlets and panels.
  • Machining, fabrication and plastics. Motor-heavy, with high starting currents. Verify three-phase 600V and demand headroom.
  • Food-grade and cold storage. Refrigeration runs continuously, so the load is sustained, not peaky. Redundancy matters.
  • High-power manufacturing. Furnaces, large presses and heavy welding can push you into primary service.
  • Data and tech infrastructure. Capacity and redundancy drive site choice before anything else.

If your use is on this list, we offer dedicated searches for high-power manufacturing space, manufacturing space and food-grade or refrigerated space.

Coordinating the building around the electrical work

A larger service is a construction project, not just a utility file. New electrical rooms, transformer pads, trenching and equipment access all touch other building elements, and the facility team has to coordinate them with the electrician. Doors, access control and egress in and around those spaces are part of that planning, and this overview of industrial door solutions for facility managers is a useful starting point for that conversation. For the tenant fit-out as a whole, see our GTA tenant fit-out planning guide and practical tenant improvement examples.

Our perspective

We see power treated as an afterthought more often than almost any other lease issue. A tenant falls in love with the clear height, the dock count and the rent, and asks about electricity last. By then the other buildings on the shortlist are gone.

Our advice is to reverse the order. Before touring, write down your design load, your voltage and phase, and your three-year growth case. Put them in the search brief. Then screen buildings on electrical capacity first and confirm with the utility before any offer goes in. A handful of buildings that truly fit beat dozens that might.

This is also where a broker earns the fee. With more than a decade in Ontario’s industrial sector and a track record that includes over $2.5B in closed industrial transactions, we know which submarkets tend to have heavier power and which buildings have been upgraded before. We bring the engineer and the utility into the process early, and we write the conditions into the lease so that you are not paying rent on a building you cannot yet run.

— Michael Law

Work with a broker who checks the power first

If you are searching for manufacturing space in Mississauga, Brampton, Vaughan, Markham or elsewhere in the GTA, we start with your load, voltage and growth plan, and screen buildings against them before you tour. Our tenant representation for industrial users covers site selection, lease negotiation and conditions tied to utility confirmation. You can see the full range on our services page, or learn more about Michael Law at Lennard Commercial.

Michael Law | Lennard Commercial

For more on how we work across the region, visit mlawrealestate.com or see our GTA industrial broker page.

FAQ

How much power does a manufacturing facility need?

It depends on the equipment, not the square footage. Build a load schedule of all machines and building systems, apply duty and power factor, and add planned growth. Then size the service so that demand stays under 80% of its rating, as the Ontario Electrical Safety Code requires.

What voltage do industrial buildings in Ontario use?

Industrial, commercial and institutional buildings in Ontario commonly use 120/208V and 347/600V distribution. Many industrial machines run on 600V three-phase, but check each nameplate. If your equipment needs a different voltage, plan for a transformer.

How long does a utility service upgrade take?

In Toronto Hydro’s territory, the quotation process typically takes up to 60 days after all information is received, and the overall project can run from weeks to years depending on complexity. Hydro One and local distribution companies have their own processes. Contact the utility serving your address as early as possible.

Can I rely on a listing that says “expandable power”?

No. Treat it as a prompt to ask questions, not an answer. Ask the landlord for single-line diagrams and existing demand, and ask the utility whether the local network can supply your design load. Make your lease conditional on that confirmation.

Who needs to inspect new electrical work in Ontario?

The Electrical Safety Authority inspects electrical installations under the Ontario Electrical Safety Code. Work is generally done by a licensed electrical contracting business, and the utility completes its own final inspection before energizing a new or upgraded service.

Sources

Michael Law

About Michael Law

Managing Partner and Industrial Real Estate Broker at Lennard Commercial Realty. Representing tenants and landlords across Toronto and the GTA for 15+ years. Michael specializes in GTA industrial real estate — connect with Toronto's leading industrial broker at mlawrealestate.com/industrial-broker-toronto.

Work with Michael →
Related Insights

More Toronto Industrial Real Estate Insights